WP6

Work Package 6

Management and coordination

WP6 handles the day-to-day management, coordination, and reporting that keep the consortium aligned — covering financial and administrative coordination, periodic project meetings, and formal reporting in line with EURAMET requirements.

TUBITAK logo WP Leader TUBITAK

Objectives

What this work package will deliver

  1. 1

    Run financial, administrative, and scientific coordination across all 17 partners.

  2. 2

    Plan and run periodic consortium meetings (kick-off, mid-term, annual, final).

  3. 3

    Submit formal reports to EURAMET according to the Reporting Guidelines.

Tasks & activities

Breakdown of work

3 tasks · 13 activities
Task 6.1

Project management

Months 1–36

Continuous coordination activities: financial management, partner liaison, contract administration, risk monitoring, and consortium agreement maintenance throughout the 36 months.

Activities (4)

A6.1.1

Project management board

Deadline: M36

TUBITAK coordinates with the project management board (one representative per participant) — guiding the project, attending meetings, and organising progress meetings at local institutes.

Participants: TUBITAK All participants
A6.1.2

WP leader reporting

Deadline: M36

Work-package leaders report on ongoing progress to the coordinator via email, calls, and virtual meetings.

Participants: TUBITAK NSAI SMU UL Random Red
A6.1.3

Risk management

Deadline: M36

Coordinator manages project risks (with participant support) to ensure timely and effective delivery of scientific/technical objectives and deliverables.

Participants: TUBITAK All participants
A6.1.4

Ethics issues management

Deadline: M36

Consortium ensures any identified ethics issues are addressed.

Participants: TUBITAK All participants
Task 6.2

Project meetings

Months 1–36

Kick-off meeting at month 2, followed by periodic consortium and steering committee meetings every ~9 months, plus ad-hoc technical meetings as needed.

Activities (3)

A6.2.1

Kick-off meeting (TUBITAK)

Deadline: M2

Kick-off meeting involving all participants — held approximately two months after project start, hosted at TUBITAK.

Participants: TUBITAK All participants
A6.2.2

Five formal project meetings

Deadline: M36

Five formal project meetings: kick-off, M9 (UL), M18 (mid-term, host TBD), M27, and M36 (final). Held prior to reporting every nine months — reviewing progress and clarifying roles for the next period.

Participants: TUBITAK All participants
A6.2.3

Ad-hoc technical WP meetings

Deadline: M36

Technical meetings of different work-package groups held as needed — organised remotely on an ad-hoc basis.

Participants: TUBITAK All participants
Task 6.3

Project reporting

Months 1–36

Formal reporting submitted in accordance with EURAMET's Reporting Guidelines: kick-off, interim, mid-term, and final reports plus any periodic financial statements.

Activities (6)

A6.3.1

Publishable summary (M1)

Deadline: M1

Publishable summary produced one month after the start of the project and submitted to EURAMET.

Participants: TUBITAK All participants
A6.3.2

Interim 1 Reports (M9 + 45 days)

Deadline: M10

Progress report, Data Management Plan (DMP), and DCE plan submitted to EURAMET at M9 (+45 days) under Articles 19 & 21 of the Grant Agreement.

Participants: TUBITAK All participants
A6.3.3

Period 1 Reports (M18 + 60 days)

Deadline: M19

Periodic progress and financial reports, outcomes, and impact reports submitted to EURAMET at M18 (+60 days).

Participants: TUBITAK All participants
A6.3.4

Interim 2 Reports (M27 + 45 days)

Deadline: M27

Interim progress report submitted to EURAMET at M27 (+45 days); includes mid-term review follow-up where applicable.

Participants: TUBITAK All participants
A6.3.5

Final & Period 2 Reports (M36 + 60 days)

Deadline: M36

Final periodic progress, financial reports, and final publishable report delivered at M36 (+60 days) — under Articles 19 & 21 of the Grant Agreement.

Participants: TUBITAK All participants
A6.3.6

Mid-term review (Spring 2028)

Deadline: M23

Mid-term review: project self-assessment, updated publishable summary, and presentation delivered prior to the EURAMET mid-term review for Call 2025 — schedule per EURAMET requirements.

Participants: TUBITAK All participants

Timeline

WP6 Gantt chart

Task spans and individual activities across the 36-month project plan (Jun 2026 — May 2029).

WP6 Gantt chart — tasks and activities across 36 project months